What is a Section 58 restriction? Road dig bans explained
Updated 4 November 2026
A Section 58 restriction is a ban on new digging in a stretch of road for a set period after the council has done substantial work on it, such as resurfacing. It comes from Section 58 of the New Roads and Street Works Act 1991, and its purpose is simple: a freshly resurfaced road shouldn't be dug up again a few weeks later.
How it works
- Notice first. Before the major work, the council gives notice so that utility companies can do any digging they need first, while the road is going to be resurfaced anyway.
- Then the restriction. Once the work is done, the restriction applies to that stretch of road for the period the council sets, often a year or more.
- Exceptions. Emergency works, such as a gas leak or a burst main, can still go ahead. Some other works, such as a new connection for a customer, may be allowed with the council's consent and conditions, for example a higher standard of reinstatement.
A related power, Section 58A, lets councils restrict further digging after substantial works by a utility company.
Who it matters to
- Developers and their solicitors. A restriction on the road outside a site can delay new water, gas, power or broadband connections. It's worth checking before exchange and keeping an eye on it through to completion.
- Utility companies and contractors planning works on a street.
- Residents. A Section 58 isn't roadworks: nothing is happening on the road. It just means the road shouldn't be dug up again soon.
How to find Section 58 restrictions
Councils in England record them in Street Manager, and LiveRoad shows them:
- On the live map, turn on the Section 58 button in the filter row. They show as a purple "58" sign.
- Checking a list of sites for your business? Talk to us.
LiveRoad only shows restrictions the council has recorded in Street Manager, so for legal work it should sit alongside your usual searches, not replace them.