Roadworks running late in Derbyshire County Council
58 roadworks are past the planned finish date with no finish reported. See all roadworks in Derbyshire County Council .
Unnamed Road Section of A6 From Buxton Road Dove Holes To Fairfield Road
DERBYSHIRE COUNTY COUNCIL · started 29 Sept 2026 · planned to finish 28 Sept 2026
25 days
Alexandra Road
DERBYSHIRE COUNTY COUNCIL · started 25 Sept 2026 · planned to finish 29 Sept 2026
24 days
Leathersley Lane
DERBYSHIRE COUNTY COUNCIL · started 14 Sept 2026 · planned to finish 29 Sept 2026
24 days
Leathersley Lane
DERBYSHIRE COUNTY COUNCIL · started 14 Sept 2026 · planned to finish 29 Sept 2026
24 days
Unnamed Road From Aston Lane To Cave Cottage
Connect Fibre (Fibre Assets Ltd) · started 17 Sept 2026 · planned to finish 29 Sept 2026
24 days
School Lane
CADENT GAS LIMITED · started 3 Sept 2026 · planned to finish 30 Sept 2026
23 days
Alsop Road
DERBYSHIRE COUNTY COUNCIL · started 14 Sept 2026 · planned to finish 1 Oct 2026
22 days
Ashbourne Road
DERBYSHIRE COUNTY COUNCIL · started 9 Aug 2026 · planned to finish 1 Oct 2026
22 days
High Street
DERBYSHIRE COUNTY COUNCIL · started 1 Oct 2026 · planned to finish 1 Oct 2026
22 days
Langwith Road
DERBYSHIRE COUNTY COUNCIL · started 29 Sept 2026 · planned to finish 1 Oct 2026
22 days
Grosvenor Road
DERBYSHIRE COUNTY COUNCIL · started 17 Aug 2026 · planned to finish 2 Oct 2026
21 days
Hallam Court
DERBYSHIRE COUNTY COUNCIL · started 29 Sept 2026 · planned to finish 2 Oct 2026
21 days
High Street
DERBYSHIRE COUNTY COUNCIL · started 23 Sept 2026 · planned to finish 2 Oct 2026
21 days
Dale Road
DERBYSHIRE COUNTY COUNCIL · started 14 Sept 2026 · planned to finish 4 Oct 2026
19 days
Talbot Street
BT · started 4 Oct 2026 · planned to finish 4 Oct 2026
19 days
Wreakes Lane
DERBYSHIRE COUNTY COUNCIL · started 24 Aug 2026 · planned to finish 5 Oct 2026
19 days
Springvale Road
CADENT GAS LIMITED · started 17 Sept 2026 · planned to finish 6 Oct 2026
17 days
Welbeck Drive
BT · started 8 Oct 2026 · planned to finish 8 Oct 2026
16 days
Bakewell Road
DERBYSHIRE COUNTY COUNCIL · started 28 Sept 2026 · planned to finish 8 Oct 2026
15 days
Bradbourne Road
DERBYSHIRE COUNTY COUNCIL · started 27 Sept 2026 · planned to finish 8 Oct 2026
15 days
Fauvel Road
DERBYSHIRE COUNTY COUNCIL · started 7 Oct 2026 · planned to finish 9 Oct 2026
15 days
Swarkestone Bridge
DERBYSHIRE COUNTY COUNCIL · started 7 Oct 2026 · planned to finish 8 Oct 2026
15 days
Unnamed Road Section of B6105 From Woodhead Road To Crowden
DERBYSHIRE COUNTY COUNCIL · started 29 Sept 2026 · planned to finish 8 Oct 2026
15 days
Derby Road
DERBYSHIRE COUNTY COUNCIL · started 28 Sept 2026 · planned to finish 9 Oct 2026
14 days
Derby Road
DERBYSHIRE COUNTY COUNCIL · started 17 Aug 2026 · planned to finish 9 Oct 2026
14 days
Dinting Road
DERBYSHIRE COUNTY COUNCIL · started 4 May 2026 · planned to finish 9 Oct 2026
14 days
Summer Lane
CADENT GAS LIMITED · started 8 Sept 2026 · planned to finish 9 Oct 2026
14 days
Sheffield Road
BT · started 13 Oct 2026 · planned to finish 13 Oct 2026
11 days
Market Place
DERBYSHIRE COUNTY COUNCIL · started 4 Oct 2026 · planned to finish 14 Oct 2026
9 days
Leicester Street
DERBYSHIRE COUNTY COUNCIL · started 9 Oct 2026 · planned to finish 16 Oct 2026
7 days
Eckington Footpath 11
SEVERN TRENT WATER · started 21 Sept 2026 · planned to finish 17 Oct 2026
6 days
Longford Lane
Connect Fibre (Fibre Assets Ltd) · started 19 Oct 2026 · planned to finish 20 Oct 2026
3 days
The Ridings
DERBYSHIRE COUNTY COUNCIL · started 20 Oct 2026 · planned to finish 21 Oct 2026
3 days
Bank Lane
SP Electricity North West · started 19 Oct 2026 · planned to finish 22 Oct 2026
2 days
Beresford Avenue
BT · started 21 Oct 2026 · planned to finish 21 Oct 2026
2 days
Maynestone Road
SP Electricity North West · started 22 Oct 2026 · planned to finish 22 Oct 2026
2 days
Boggy Lane
National Grid Electricity Distribution (East Midlands) · started 13 Oct 2026 · planned to finish 22 Oct 2026
1 day
Breedon Street
DERBYSHIRE COUNTY COUNCIL · started 21 Oct 2026 · planned to finish 23 Oct 2026
1 day
Castle Road
CADENT GAS LIMITED · started 10 Oct 2026 · planned to finish 23 Oct 2026
1 day
Church Street East
VIRGIN MEDIA · started 21 Oct 2026 · planned to finish 23 Oct 2026
1 day
Coach Road
DERBYSHIRE COUNTY COUNCIL · started 19 Oct 2026 · planned to finish 23 Oct 2026
1 day
Furlong Lane
BT · started 22 Oct 2026 · planned to finish 23 Oct 2026
1 day
Green Lane
National Grid Electricity Distribution (East Midlands) · started 19 Oct 2026 · planned to finish 23 Oct 2026
1 day
Grosvenor Avenue
DERBYSHIRE COUNTY COUNCIL · started 19 Oct 2026 · planned to finish 23 Oct 2026
1 day
High Street
CADENT GAS LIMITED · started 15 Oct 2026 · planned to finish 23 Oct 2026
1 day
Main Road
SEVERN TRENT WATER · started 22 Oct 2026 · planned to finish 22 Oct 2026
1 day
Main Street
DERBYSHIRE COUNTY COUNCIL · started 15 Oct 2026 · planned to finish 23 Oct 2026
1 day
Newlands Road
CADENT GAS LIMITED · started 14 Oct 2026 · planned to finish 23 Oct 2026
1 day
Prince Street
SEVERN TRENT WATER · started 21 Oct 2026 · planned to finish 22 Oct 2026
1 day
Simmondley New Road
SP Electricity North West · started 18 Oct 2026 · planned to finish 23 Oct 2026
1 day
Stormont Close
DERBYSHIRE COUNTY COUNCIL · started 6 Oct 2026 · planned to finish 22 Oct 2026
1 day
Thatchers Lane
National Grid Electricity Distribution (East Midlands) · started 19 Oct 2026 · planned to finish 22 Oct 2026
1 day
The Pastures
CADENT GAS LIMITED · started 15 Oct 2026 · planned to finish 23 Oct 2026
1 day
Valley Road
SP Electricity North West · started 5 Oct 2026 · planned to finish 22 Oct 2026
1 day
Walton Back Lane
YORKSHIRE WATER · started 22 Oct 2026 · planned to finish 22 Oct 2026
1 day
Walton Drive
National Grid Electricity Distribution (East Midlands) · started 21 Oct 2026 · planned to finish 22 Oct 2026
1 day
Wirksworth Road
DERBYSHIRE COUNTY COUNCIL · started 22 Oct 2026 · planned to finish 22 Oct 2026
1 day
Wirksworth Road
National Grid Electricity Distribution (East Midlands) · started 20 Oct 2026 · planned to finish 22 Oct 2026
1 day
Share this list
These works were reported as started, their planned end date has passed, and the operator hasn't reported a finish to Street Manager. Some may have finished without reporting it; a permit extension also shows as a new end date once it's filed. FixMyStreet passes reports to the right council.