Roadworks running late in Hull City Council
45 roadworks are past the planned finish date with no finish reported. See all roadworks in Hull City Council .
Holderness Road
HULL CITY COUNCIL · started 28 Sept 2026 · planned to finish 28 Sept 2026
25 days
Kesteven Way
HULL CITY COUNCIL · started 28 Sept 2026 · planned to finish 28 Sept 2026
25 days
North Road
HULL CITY COUNCIL · started 28 Sept 2026 · planned to finish 28 Sept 2026
25 days
Summergangs Road
HULL CITY COUNCIL · started 25 Sept 2026 · planned to finish 28 Sept 2026
25 days
Wawne Road
HULL CITY COUNCIL · started 28 Sept 2026 · planned to finish 28 Sept 2026
25 days
Boothferry Road
HULL CITY COUNCIL · started 21 Sept 2026 · planned to finish 29 Sept 2026
24 days
Bude Road
HULL CITY COUNCIL · started 29 Sept 2026 · planned to finish 29 Sept 2026
24 days
Cumberland Street
HULL CITY COUNCIL · started 21 Sept 2026 · planned to finish 29 Sept 2026
24 days
East Park Avenue
HULL CITY COUNCIL · started 21 Sept 2026 · planned to finish 29 Sept 2026
24 days
Holwell Road
HULL CITY COUNCIL · started 29 Sept 2026 · planned to finish 29 Sept 2026
24 days
Saltshouse Road
HULL CITY COUNCIL · started 21 Sept 2026 · planned to finish 29 Sept 2026
24 days
Marfleet Lane
HULL CITY COUNCIL · started 7 Sept 2026 · planned to finish 30 Sept 2026
23 days
Leads Road
HULL CITY COUNCIL · started 1 Oct 2026 · planned to finish 1 Oct 2026
22 days
Summergangs Road
NORTHERN GAS NETWORKS · started 8 Sept 2026 · planned to finish 1 Oct 2026
22 days
5th Avenue
HULL CITY COUNCIL · started 25 Sept 2026 · planned to finish 2 Oct 2026
21 days
Clough Road
HULL CITY COUNCIL · started 25 Sept 2026 · planned to finish 2 Oct 2026
21 days
Saltshouse Road
YORKSHIRE WATER · started 30 Sept 2026 · planned to finish 6 Oct 2026
17 days
Spring Bank West
HULL CITY COUNCIL · started 6 Oct 2026 · planned to finish 7 Oct 2026
16 days
Fpath at Topcliffe Garth
NORTHERN GAS NETWORKS · started 7 Sept 2026 · planned to finish 8 Oct 2026
15 days
Village Road
HULL CITY COUNCIL · started 28 Sept 2026 · planned to finish 8 Oct 2026
15 days
32nd Avenue
HULL CITY COUNCIL · started 6 Oct 2026 · planned to finish 9 Oct 2026
14 days
St James Street
HULL CITY COUNCIL · started 5 Oct 2026 · planned to finish 9 Oct 2026
14 days
Endike Lane
NORTHERN GAS NETWORKS · started 27 Jul 2026 · planned to finish 12 Oct 2026
11 days
Richmond Way
ESP ELECTRICITY · started 7 Sept 2026 · planned to finish 15 Oct 2026
8 days
Richmond Way
E S PIPELINES LTD · started 7 Sept 2026 · planned to finish 15 Oct 2026
8 days
Albion Street
HULL CITY COUNCIL · started 12 Oct 2026 · planned to finish 16 Oct 2026
7 days
Clough Road
HULL CITY COUNCIL · started 13 Oct 2026 · planned to finish 16 Oct 2026
7 days
Cumbrian Way
HULL CITY COUNCIL · started 12 Oct 2026 · planned to finish 16 Oct 2026
7 days
Dairycoates Avenue
HULL CITY COUNCIL · started 8 Oct 2026 · planned to finish 16 Oct 2026
7 days
Ecclesfield Avenue
HULL CITY COUNCIL · started 12 Oct 2026 · planned to finish 16 Oct 2026
7 days
English Street
HULL CITY COUNCIL · started 13 Oct 2026 · planned to finish 16 Oct 2026
7 days
Fpath From Holwell Road To Tiverton Road Near Soffham Close
HULL CITY COUNCIL · started 12 Oct 2026 · planned to finish 16 Oct 2026
7 days
Greenwood Avenue
HULL CITY COUNCIL · started 13 Oct 2026 · planned to finish 16 Oct 2026
7 days
Lowgate
HULL CITY COUNCIL · started 13 Oct 2026 · planned to finish 16 Oct 2026
7 days
Gloucester Street
NORTHERN GAS NETWORKS · started 20 Oct 2026 · planned to finish 20 Oct 2026
3 days
Anlaby Park Road South
NORTHERN GAS NETWORKS · started 18 Oct 2026 · planned to finish 22 Oct 2026
2 days
Carr Lane
NORTHERN GAS NETWORKS · started 17 Oct 2026 · planned to finish 22 Oct 2026
2 days
Cropton Road
NORTHERN GAS NETWORKS · started 18 Oct 2026 · planned to finish 22 Oct 2026
2 days
Greylees Avenue
NORTHERN POWERGRID (YORKSHIRE) PLC · started 16 Oct 2026 · planned to finish 22 Oct 2026
2 days
Burleigh Street
NORTHERN GAS NETWORKS · started 12 Oct 2026 · planned to finish 22 Oct 2026
1 day
Francis Street
NORTHERN GAS NETWORKS · started 12 Oct 2026 · planned to finish 23 Oct 2026
1 day
Hessle Road
NORTHERN POWERGRID (YORKSHIRE) PLC · started 19 Oct 2026 · planned to finish 23 Oct 2026
1 day
Houghton Walk
NORTHERN GAS NETWORKS · started 14 Oct 2026 · planned to finish 23 Oct 2026
1 day
Laburnum Avenue
HULL CITY COUNCIL · started 28 Sept 2026 · planned to finish 22 Oct 2026
1 day
Laburnum Avenue
HULL CITY COUNCIL · started 28 Sept 2026 · planned to finish 22 Oct 2026
1 day
Share this list
These works were reported as started, their planned end date has passed, and the operator hasn't reported a finish to Street Manager. Some may have finished without reporting it; a permit extension also shows as a new end date once it's filed. FixMyStreet passes reports to the right council.