Roadworks running late in London Borough of Merton
27 roadworks are past the planned finish date with no finish reported. See all roadworks in London Borough of Merton .
Merton High Street
THAMES WATER · started 19 Jun 2026 · planned to finish 24 Sept 2026
29 days
Wandle Bank
THAMES WATER · started 9 Jul 2026 · planned to finish 24 Sept 2026
29 days
Hyde Walk
LONDON BOROUGH OF MERTON · started 2 Oct 2026 · planned to finish 29 Sept 2026
24 days
Recreation Way
SOUTHERN GAS NETWORKS PLC · started 2 Feb 2026 · planned to finish 29 Sept 2026
24 days
Queen's Road
LONDON BOROUGH OF MERTON · started 30 Jun 2026 · planned to finish 30 Sept 2026
23 days
Chester Road
LONDON BOROUGH OF MERTON · started 29 Sept 2026 · planned to finish 1 Oct 2026
22 days
Chester Road
LONDON BOROUGH OF MERTON · started 29 Sept 2026 · planned to finish 1 Oct 2026
22 days
Homefield Road
LONDON BOROUGH OF MERTON · started 2 Oct 2026 · planned to finish 6 Oct 2026
17 days
Prince Georges Road
LAST MILE ELECTRICITY LIMITED (Formerly GLOBAL UTILITY CONNECTIONS) · started 16 Sept 2026 · planned to finish 8 Oct 2026
15 days
Bond Road
LONDON BOROUGH OF MERTON · started 9 Sept 2026 · planned to finish 9 Oct 2026
14 days
Cavendish Avenue
SOUTHERN GAS NETWORKS PLC · started 6 Oct 2026 · planned to finish 13 Oct 2026
11 days
Montacute Road
SOUTHERN GAS NETWORKS PLC · started 17 Aug 2026 · planned to finish 13 Oct 2026
10 days
Laings Avenue
THAMES WATER · started 8 Oct 2026 · planned to finish 14 Oct 2026
9 days
Wilton Crescent
LONDON BOROUGH OF MERTON · started 7 Sept 2026 · planned to finish 15 Oct 2026
8 days
Copse Hill
SOUTHERN GAS NETWORKS PLC · started 20 Jul 2026 · planned to finish 17 Oct 2026
6 days
Brook Close
THAMES WATER · started 5 Oct 2026 · planned to finish 18 Oct 2026
5 days
Havelock Road
THAMES WATER · started 1 Sept 2026 · planned to finish 19 Oct 2026
4 days
Coppice Close
THAMES WATER · started 12 Oct 2026 · planned to finish 20 Oct 2026
3 days
Templecombe Way
SES WATER (Formerly SUTTON & EAST SURREY WATER COMPANY) · started 22 Oct 2026 · planned to finish 22 Oct 2026
2 days
Woodside
THAMES WATER · started 20 Oct 2026 · planned to finish 21 Oct 2026
2 days
Belvedere Grove
THAMES WATER · started 21 Oct 2026 · planned to finish 22 Oct 2026
1 day
Berkeley Place
BT · started 22 Oct 2026 · planned to finish 23 Oct 2026
1 day
Central Road
SES WATER (Formerly SUTTON & EAST SURREY WATER COMPANY) · started 19 Oct 2026 · planned to finish 22 Oct 2026
1 day
Cochrane Road
THAMES WATER · started 2 Oct 2026 · planned to finish 22 Oct 2026
1 day
Inglemere Road
LONDON BOROUGH OF MERTON · started 21 Oct 2026 · planned to finish 22 Oct 2026
1 day
Lansdowne Road
BT · started 22 Oct 2026 · planned to finish 23 Oct 2026
1 day
Rosevine Road
THAMES WATER · started 21 Oct 2026 · planned to finish 23 Oct 2026
1 day
Share this list
These works were reported as started, their planned end date has passed, and the operator hasn't reported a finish to Street Manager. Some may have finished without reporting it; a permit extension also shows as a new end date once it's filed. FixMyStreet passes reports to the right council.