67 roadworks are past the planned finish date with no finish reported. See all roadworks in Northumberland County Council .
U3023 Dene House Junction To Hawkhill Junction
NORTHUMBERLAND COUNTY COUNCIL · started 6 Jul 2026 · planned to finish 25 Sept 2026
28 days
B6309 Welton To Whittle Dene Reservoir
NORTHUMBRIAN WATER · started 22 Jun 2026 · planned to finish 1 Oct 2026
22 days
The Haven
BT · started 30 Sept 2026 · planned to finish 2 Oct 2026
21 days
Twelfth Avenue
NORTHERN POWERGRID (NORTHEAST) PLC · started 30 Sept 2026 · planned to finish 5 Oct 2026
18 days
Forum Way
NORTHERN GAS NETWORKS · started 18 Sept 2026 · planned to finish 7 Oct 2026
16 days
C106 Alnwick Fords To Newton on the Moor
NORTHUMBRIAN WATER · started 19 May 2026 · planned to finish 8 Oct 2026
15 days
Netherton Road
NORTHUMBERLAND COUNTY COUNCIL · started 19 Aug 2026 · planned to finish 8 Oct 2026
15 days
North Seaton Road
NORTHUMBRIAN WATER · started 21 Sept 2026 · planned to finish 8 Oct 2026
15 days
A695 Hexham To Dilston
NORTHUMBERLAND COUNTY COUNCIL · started 29 Jun 2026 · planned to finish 9 Oct 2026
14 days
Allendale Road
NORTHUMBERLAND COUNTY COUNCIL · started 12 Oct 2026 · planned to finish 14 Oct 2026
10 days
C404 Moorland Avenue To Spring Ville
NORTHUMBERLAND COUNTY COUNCIL · started 4 Oct 2026 · planned to finish 16 Oct 2026
8 days
Chestnut Street
NORTHERN GAS NETWORKS · started 9 Oct 2026 · planned to finish 15 Oct 2026
8 days
Churchburn Drive
NORTHUMBERLAND COUNTY COUNCIL · started 12 Oct 2026 · planned to finish 16 Oct 2026
8 days
Maple Street Back Lane 253-297
NORTHERN GAS NETWORKS · started 16 Oct 2026 · planned to finish 15 Oct 2026
8 days
Mirlaw Road
NORTHUMBERLAND COUNTY COUNCIL · started 16 Oct 2026 · planned to finish 16 Oct 2026
8 days
Park Avenue
NORTHUMBERLAND COUNTY COUNCIL · started 14 Oct 2026 · planned to finish 16 Oct 2026
8 days
Rosalind Avenue
NORTHERN GAS NETWORKS · started 21 Sept 2026 · planned to finish 15 Oct 2026
8 days
U6523 U6524 U6525 U6526 U6527 Chestnut Street Back Lane
NORTHERN GAS NETWORKS · started 16 Oct 2026 · planned to finish 15 Oct 2026
8 days
U9561 Cramlington Town Centre Cycle Track South
NORTHUMBERLAND COUNTY COUNCIL · started 5 Oct 2026 · planned to finish 16 Oct 2026
8 days
A189 Spine Road Moor Farm To Kitty Brewster Bridge
NORTHUMBERLAND COUNTY COUNCIL · started 15 Oct 2026 · planned to finish 17 Oct 2026
7 days
C236 Wall To Brunton Bank
NORTHUMBERLAND COUNTY COUNCIL · started 5 Oct 2026 · planned to finish 16 Oct 2026
7 days
Chase Farm Drive
BT · started 12 Oct 2026 · planned to finish 16 Oct 2026
7 days
Harbour Road
NORTHUMBERLAND COUNTY COUNCIL · started 6 Apr 2026 · planned to finish 16 Oct 2026
7 days
Thoroton Street
NORTHUMBERLAND COUNTY COUNCIL · started 14 Sept 2026 · planned to finish 16 Oct 2026
7 days
A189 Spine Road Moor Farm To Kitty Brewster Bridge
NORTHUMBERLAND COUNTY COUNCIL · started 15 Oct 2026 · planned to finish 17 Oct 2026
6 days
Aln Street
NORTHUMBERLAND COUNTY COUNCIL · started 13 Oct 2026 · planned to finish 19 Oct 2026
5 days
Woodhorn Villas
NORTHUMBERLAND COUNTY COUNCIL · started 13 Oct 2026 · planned to finish 19 Oct 2026
5 days
Chichester Avenue
NORTHUMBERLAND COUNTY COUNCIL · started 14 Oct 2026 · planned to finish 20 Oct 2026
4 days
Gordon Road
NORTHUMBERLAND COUNTY COUNCIL · started 16 Oct 2026 · planned to finish 20 Oct 2026
4 days
Nelson Avenue
NORTHUMBERLAND COUNTY COUNCIL · started 14 Oct 2026 · planned to finish 20 Oct 2026
4 days
Ross Grove
NORTHUMBERLAND COUNTY COUNCIL · started 14 Oct 2026 · planned to finish 20 Oct 2026
4 days
Solingen Estate
NORTHUMBERLAND COUNTY COUNCIL · started 16 Oct 2026 · planned to finish 20 Oct 2026
4 days
U6523 Hawthorn Road Chestnut Street Back Lane
NORTHERN GAS NETWORKS · started 6 Oct 2026 · planned to finish 19 Oct 2026
4 days
U9049 Road To West Newham
NORTHUMBRIAN WATER · started 7 Sept 2026 · planned to finish 19 Oct 2026
4 days
Wensleydale Terrace
NORTHUMBERLAND COUNTY COUNCIL · started 16 Oct 2026 · planned to finish 20 Oct 2026
4 days
Seaton Avenue North View Footway
NORTHERN GAS NETWORKS · started 13 Oct 2026 · planned to finish 22 Oct 2026
2 days
U8275 Westacres Footway
BT · started 19 Oct 2026 · planned to finish 21 Oct 2026
2 days
U8302 Old Bridge
NORTHUMBERLAND COUNTY COUNCIL · started 19 Oct 2026 · planned to finish 21 Oct 2026
2 days
A6079 Wall To Chollerton
BROADBAND FOR THE RURAL NORTH LTD · started 21 Oct 2026 · planned to finish 23 Oct 2026
1 day
B1505 Albion Terrace To Bog Houses
Zayo Europe · started 21 Oct 2026 · planned to finish 23 Oct 2026
1 day
B1505 Klondyke
NORTHERN GAS NETWORKS · started 7 Oct 2026 · planned to finish 23 Oct 2026
1 day
B6309 Stamfordham To Burnside
NORTHUMBRIAN WATER · started 15 Jun 2026 · planned to finish 23 Oct 2026
1 day
B6318 Chollerford To Brunton Cross Roads
BROADBAND FOR THE RURAL NORTH LTD · started 22 Oct 2026 · planned to finish 23 Oct 2026
1 day
B6341 Bilsmoor To Thropton
NORTHUMBERLAND COUNTY COUNCIL · started 19 Oct 2026 · planned to finish 22 Oct 2026
1 day
B6341 Elsdon To Bilsmoor
NORTHUMBERLAND COUNTY COUNCIL · started 19 Oct 2026 · planned to finish 22 Oct 2026
1 day
B6354 Ford Bridge Junction To Tweedmouth
NORTHUMBERLAND COUNTY COUNCIL · started 19 Oct 2026 · planned to finish 23 Oct 2026
1 day
B6525 Barmoor To Ancroft
NORTHUMBERLAND COUNTY COUNCIL · started 20 Oct 2026 · planned to finish 22 Oct 2026
1 day
Beamsley Terrace
NORTHUMBRIAN WATER · started 19 Oct 2026 · planned to finish 22 Oct 2026
1 day
Beech Avenue
NORTHUMBERLAND COUNTY COUNCIL · started 15 Oct 2026 · planned to finish 22 Oct 2026
1 day
Briardale Road
NORTHUMBRIAN WATER · started 21 Oct 2026 · planned to finish 22 Oct 2026
1 day
Bristol Street
Zayo Europe · started 19 Oct 2026 · planned to finish 23 Oct 2026
1 day
Broom Close
NORTHUMBERLAND COUNTY COUNCIL · started 15 Oct 2026 · planned to finish 22 Oct 2026
1 day
C172 Whittingham Village
NORTHERN POWERGRID (NORTHEAST) PLC · started 8 Oct 2026 · planned to finish 23 Oct 2026
1 day
Charlton Gardens
NORTHUMBERLAND COUNTY COUNCIL · started 15 Oct 2026 · planned to finish 22 Oct 2026
1 day
Front Street West
NORTHUMBRIAN WATER · started 19 Oct 2026 · planned to finish 22 Oct 2026
1 day
Glovers Place
NORTHERN POWERGRID (NORTHEAST) PLC · started 19 Oct 2026 · planned to finish 22 Oct 2026
1 day
Green Lane
NORTHUMBERLAND COUNTY COUNCIL · started 15 Oct 2026 · planned to finish 22 Oct 2026
1 day
Lime Grove
NORTHERN POWERGRID (NORTHEAST) PLC · started 18 Oct 2026 · planned to finish 23 Oct 2026
1 day
Main Street
NORTHUMBRIAN WATER · started 19 Oct 2026 · planned to finish 23 Oct 2026
1 day
Middle Drive
NORTHERN GAS NETWORKS · started 9 Oct 2026 · planned to finish 23 Oct 2026
1 day